The planned timetable for the project is outlined in the table below. Site Set Up
| Date | Planned Works | | May 2009 | Set up site compounds at Trevalga, Forrabury and for the pipeline works | Pipelines
| Date | Planned Works | | June to October 2009 | Forrabury to Trevalga WWTW including Trevalga Hamlet section | August to October 2009 | Bossiney to Back Lane Pumping Station | August to September 2009 | Bossiney Outfall repairs | September to November 2009 | Back Lane Pumping Station to Tintagel | October to Early December 2009 | Road section through Rocky Valley on the B3263 | November/Early December 2009 | Road section at Welltown on the B3263 | November to December 2009 | Tintagel to Castle Road Pumping Station | November to December 2009 | Forrabury to New Road Pumping Station | | January 2010 | Castle Road Pumping Station to Tintagel Haven | January to February 2010 | Boscastle Harbour Pumping Station to New Road Pumping Station | October 2009 | Back Lane Pumping Station to Outfall | Pumping Stations
| Date | Planned Works | | June to September 2009 | Boscastle Forrabury PS | | August to November 2009 | Bossiney Back Lane PS | | Late September to February 2010 | Tintagel Castle Road PS | | Mid October to February 2010 | Boscastle New Road PS | | January to February 2010 | Tintagel Haven PS | | January to February 2010 | Boscastle Harbour | | February to early March 2010 | Cover slab on Boscastle outfall | Sewage Treatment Works
| Date | Planned Works | | September to October 2009 | Tank construction | | October to January 2009 | Inlet works and control building | | November to January 2009 | Pump and tank chambers | | December to mid-March 2010 | Mechanical equipment, ducting and cable installation | | February 2010 | Odour control unit installed | | February to March 2010 | Sludge plant | | March to April 2010 | Final finishes including landscaping | | Spring 2010 | Waste water system commissioning |
|