| Date | What we will be doing | |
| w/c 25 March 2013 | Landscaping to site entrance in Coffee Lake Meadow | |
| w/c 18 March 2013 | Taking deliveries of equipment and materials Removing some equipment and materials from site Topsoil around access road General clearance of the site | |
| w/c 11 March 2013 | Taking deliveries of equipment and materials Removing some equipment from site Topsoil field around shaft and access road General clearance of the site Coffa Bridge drainage scheme | |
| w/c 4 March 2013 | Taking deliveries of equipment and materials Removing some equipment from site Backfill and topsoil field around shaft General clearance of the site Coffa Bridge drainage scheme | |
| w/c 25 February 2013 | Taking deliveries of equipment and materials Removing some equipment from site Backfill and topsoil shaft and surrounding area General clearance of the site Coffa Bridge drainage scheme | |
| w/c 18 February 2013 | Taking deliveries of equipment and materials Removing some equipment from site Mechanical and electrical installations Backfill and topsoil shaft and surrounding area General clearance of the site | |
| w/c 11 February 2013 | Taking deliveries of equipment and materials Removing some equipment from site Mechanical and electrical installations Backfill and topsoil shaft and surrounding area General clearance of the site | |
| w/c 4 February 2013 | Taking deliveries of equipment and materials Removing some equipment from site Mechanical and electrical installations Backfill and topsoil shaft and surrounding area General clearance of the site | |
| w/c 28 January 2013 | Constructing shaft and roof access chamber Taking deliveries of equipment and materials Removing some equipment from site Pipe and electrical fittings for the tank Backfill and topsoil shaft and surrounding area Installing electrics | |
| w/c 21 January 2013 | Constructing shaft and roof access chamber Earthworks to support manhole construction Taking deliveries of equipment and materials Removing some equipment from site Pipe and electrical fittings for the tank Backfilling over shaft and surrounding area Constructing base of kiosk and installing electrics | |
| w/c 14 January 2013 | Constructing shaft and roof access chamber Earthworks to support manhole construction Taking deliveries of equipment and materials Removing some equipment from site Pipe and electrical fittings for the tank Backfilling over shaft and surrounding area Constructing base of kiosk and installing electrics | |
| Saturday 22 December 2012 to Sunday 6 January 2013 | Site shut down over Christmas and New Year break. | |
| w/c 17 December 2012 | Constructing shaft and roof access chamber Earthworks to support manhole construction Taking deliveries of equipment and materials Removing some equipment from site Pipe and electrical fittings for the tank | |
| w/c 10 December 2012 | Constructing shaft and roof access chamber Earthworks to support manhole construction Taking deliveries of equipment and materials Removing some equipment from site Pipe and electrical fittings for the tank | |
| w/c 3 December 2012 | Constructing shaft and roof access chamber Earthworks to support manhole construction Taking deliveries of equipment and materials Removing some equipment from site Pumping groundwater from construction site to field Tuesday 4 December - crawler crane being moved from site through Coffee Lake Meadow, Lanwithan Road and Grenville Road. A second letter drop to remind residents will take pace on Monday 3 December. | |
| w/c 26 November 2012 | Constructing the shaft Taking deliveries of construction materials including stone, beams and sections of roof Removing some equipment from site including the crane Pumping groundwater from construction site to field Monday 26 November 2012 - concrete pour of approximately 100 cubic metres during approved delivery hours | |
| w/c 19 November 2012 | Constructing the shaft Taking deliveries of construction materials including stone, beams and sections of roof Removing some equipment from site Pumping groundwater from construction site to field Thursday 22 November 2012 - concrete pour of approximately 100 cubic metres during approved delivery hours (TBC) | |
| w/c 12 November 2012 | Constructing the shaft Taking deliveries of construction materials including pre-cast concrete items and stone Removing some equipment from site Pumping groundwater from construction site to field | |
| w/c 5 November 2012 | Constructing the shaft Taking deliveries of construction materials including pre-cast concrete items Removing some equipment from site Pumping groundwater from construction site to field Tuesday 6 November 2012 - we will be taking delivery of a wide load. Affected residents will receive a letter asking them not to park on the proposed route of Grenville Road, Lanwithan Road and Coffee Lake Meadow from the afternoon of Monday 5 November | |
| w/c 29 October 2012 | Constructing the shaft Taking deliveries of construction materials including pre-cast concrete items and stone Removing some equipment from site Pumping groundwater from construction site to field | |
| w/c 22 October 2012 | Construction of the shaft Taking deliveries of construction materials including pre-cast concrete items Removing some equipment from site Pumping groundwater from construction site to field Concrete pour scheduled for some time this week, details to follow | |
| Friday 19 October 2012 TBC | A large amount of concrete will be delivered to the construction site. This will mean an increase in vehicle movements throughout the day. Deliveries will start at 6.45am and work will take up to 12 hours. The delivery route will be along Grenville Road and Two Trees Road to Coffee Lake Meadow and exiting along Lanwithen Road back to Grenville Road. We will be working hard to minimise any inconvenience this may cause and to complete this phase of the works as quickly as possible. | |
| w/c 15 October 2012 | Construction of the shaft continuing Taking deliveries of construction materials including pre-cast concrete sections Pumping groundwater from construction site to field Concrete pour scheduled for Monday 15 or Tuesday 16, weather permitting | |
| w/c 8 October 2012 | Construction of the shaft continuing Taking deliveries of construction materials Removing some shaft equipment from site Pumping groundwater from construction site to field Concrete installation to the shaft scheduled w/c 15 October | |
| w/c 1 October 2012 | Further stripping of top soil from field next to Coffee Lake Meadow Construction of the shaft ongoing Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials Removing some equipment from site Continue pumping groundwater from construction site to field Delivery of drilling machine and for construction under the River Fowey to Coulson Park | |
| w/c 24 September 2012 | Stripping top soil from field next to Coffee Lake Meadow Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials Removing some equipment from site Pumping groundwater from construction site to field | |
| Wednesday 19 September | A large amount of concrete will be delivered to the construction site. This will mean an increase in vehicle movements throughout the day. Deliveries will start at 6.45am and work will take up to 12 hours. The delivery route will be along Grenville Road and Two Trees Road to Coffee Lake Meadow and exiting along Lanwithen Road back to Grenville Road. We will be working hard to minimise any inconvenience this may cause and to complete this phase of the works as quickly as possible. | |
| w/c 17 September 2012 | Stripping top soil from field next to Coffee Lake Meadow Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials Removing some equipment from site Pumping groundwater from construction site to field | |
| w/c 10 September 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating final soil from shaft Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials, including reinforcement and cement Removing some equipment from site | |
| w/c 3 September 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating final soil from shaft Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials, including reinforcement and cement Removing some equipment from site Pumping groundwater from construction site to field | |
| w/c 27 August 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating shaft Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of construction materials Pumping groundwater from construction site to field | |
| w/c 20 August 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating shaft Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of shaft rings and general construction materials Pumping groundwater from construction site to field | |
| w/c 13 August 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating shaft Constructing shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of shaft rings and general construction materials Pumping groundwater from construction site to field | |
| w/c 6 August 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating shaft Preparing to construct shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of shaft rings and general construction materials Pumping groundwater from construction site to field Taking deliveries of concrete ready for pouring on Tuesday 7 August | |
| w/c 30 July 2012 | Stripping top soil from field next to Coffee Lake Meadow Excavating shaft Preparing to construct shaft Transporting excavated material from shaft to field next to Coffee Lake Meadow Taking deliveries of shaft rings and general construction materials Pumping groundwater from construction site to field Taking deliveries of concrete ready for pouring on Thursday 2 August and Monday 6 August | |
| w/c 23 July 2012 | Installing crane next to shaft Stripping top soil around the shaft Stripping top soil from the field, ready to receive excavated material from shaft Starting to excavate the shaft Preparation works for shaft construction Transporting excavated material from shaft to field Starting to reprofile the field with excavated material Taking deliveries of shaft rings and general construction materials Continuing to move excess ground water from site to field | |
| w/c 16 July 2012 | Crane and excavator arrive on site (planned for 18/7/12) via route shown on website Installing crane foundation next to shaft Finishing installing de-watering equipment Commencing de-watering Stripping top soil around the shaft Stripping top soil from the field, ready to receive excavated material from shaft Starting excavating the shaft Preparation works for shaft construction Transporting excavated material from shaft to field Starting to reprofile the field with excavated material Taking deliveries of shaft rings and general construction materials | |
| w/c 9 July 2012 | Continuing construction of access road and temporary compound (near completion) Constructing storage area within the field near shaft Stock fencing works in field adjacent to site access Setting up temporary site office Erecting site signage at main gates Taking deliveries of de-watering equipment and setting up equipment Taking general site deliveries to complete site set up Taking deliveries of materials for shaft construction work | |
| w/c 2 July 2012 | Continuing construction of access road and temporary compound Continuing to strip top soil Constructing storage area Setting up temporary site office Widening junction of Two Trees Road and Lanwithan Road Trimming tree branches along Lanwithan Road Erecting site signage at main gates Taking delivery of de-watering equipment Starting to de-water site next to shaft Erecting timber fence | |
| w/c 25 June 2012 | Continuing to record condition of properties in Coffee Lake Meadow Continuing construction of access road and temporary compound Continuing to strip top soil along access route Ongoing construction of access road Setting up temporary site office Continuing to establish passing and holding bay on Two Trees Road Erecting site signage at main gates | |
| w/c 18 June 2012 | Continuing to record condition of properties in Coffee Lake Meadow Continuing construction of access road and temporary compound Continuing to strip top soil along access route Ongoing construction of access road Setting up temporary site office Erecting site signage at main gates Establishing passing and holding bay on Two Trees Road | |
| w/c 11 June 2012 | Erecting information board Fully recording condition of properties in Coffee Lake Meadow Starting construction of access road and temporary compound Continuing to strip top soil along access route Ongoing construction of access road Setting up temporary site office Meeting with residents liaison group | |
| w/c 6 June 2012 | Initial recording of condition of properties in Coffee Lake Meadow Erecting signs for construction traffic access route to site Delivering small plant and equipment to site Breaking through hedge to Coffee Lake Meadow Stripping top soil along access route Erecting temporary fencing around site access and compound areas | |