left corner image Domestic customersWaterLiveBusiness customersEnvironmentAbout usHelp & FAQs right corner image

Timetable of work


What to expect over the coming weeks and months:
DateWhat we will be doing
w/c 25 March 2013Landscaping to site entrance in Coffee Lake Meadow
w/c 18 March 2013Taking deliveries of equipment and materials
Removing some equipment and materials from site
Topsoil around access road
General clearance of the site
w/c 11 March 2013

Taking deliveries of equipment and materials
Removing some equipment from site
Topsoil field around shaft and access road
General clearance of the site
Coffa Bridge drainage scheme

w/c 4 March 2013

Taking deliveries of equipment and materials
Removing some equipment from site
Backfill and topsoil field around shaft
General clearance of the site
Coffa Bridge drainage scheme

w/c 25 February 2013Taking deliveries of equipment and materials
Removing some equipment from site
Backfill and topsoil shaft and surrounding area
General clearance of the site
Coffa Bridge drainage scheme
w/c 18 February 2013Taking deliveries of equipment and materials
Removing some equipment from site
Mechanical and electrical installations
Backfill and topsoil shaft and surrounding area
General clearance of the site
w/c 11 February 2013

Taking deliveries of equipment and materials
Removing some equipment from site
Mechanical and electrical installations
Backfill and topsoil shaft and surrounding area
General clearance of the site

w/c 4 February 2013

Taking deliveries of equipment and materials
Removing some equipment from site
Mechanical and electrical installations
Backfill and topsoil shaft and surrounding area
General clearance of the site

w/c 28 January 2013Constructing shaft and roof access chamber
Taking deliveries of equipment and materials
Removing some equipment from site
Pipe and electrical fittings for the tank
Backfill and topsoil shaft and surrounding area
Installing electrics
w/c 21 January 2013Constructing shaft and roof access chamber
Earthworks to support manhole construction
Taking deliveries of equipment and materials
Removing some equipment from site
Pipe and electrical fittings for the tank
Backfilling over shaft and surrounding area
Constructing base of kiosk and installing electrics
w/c 14 January 2013 Constructing shaft and roof access chamber
Earthworks to support manhole construction
Taking deliveries of equipment and materials
Removing some equipment from site
Pipe and electrical fittings for the tank
Backfilling over shaft and surrounding area
Constructing base of kiosk and installing electrics
Saturday 22 December 2012 to Sunday 6 January 2013Site shut down over Christmas and New Year break.
w/c 17 December 2012Constructing shaft and roof access chamber
Earthworks to support manhole construction
Taking deliveries of equipment and materials
Removing some equipment from site
Pipe and electrical fittings for the tank
w/c 10 December 2012Constructing shaft and roof access chamber
Earthworks to support manhole construction
Taking deliveries of equipment and materials
Removing some equipment from site
Pipe and electrical fittings for the tank
w/c 3 December 2012

Constructing shaft and roof access chamber
Earthworks to support manhole construction
Taking deliveries of equipment and materials
Removing some equipment from site
Pumping groundwater from construction site to field
Tuesday 4 December - crawler crane being moved from site through Coffee Lake Meadow, Lanwithan Road and Grenville Road. A second letter drop to remind residents will take pace on Monday 3 December.

w/c 26 November 2012Constructing the shaft
Taking deliveries of construction materials including stone, beams and sections of roof
Removing some equipment from site including the crane
Pumping groundwater from construction site to field
Monday 26 November 2012 - concrete pour of approximately 100 cubic metres during approved delivery hours
w/c 19 November 2012Constructing the shaft
Taking deliveries of construction materials including stone, beams and sections of roof
Removing some equipment from site
Pumping groundwater from construction site to field
Thursday 22 November 2012 - concrete pour of approximately 100 cubic metres during approved delivery hours (TBC)
w/c 12 November 2012Constructing the shaft
Taking deliveries of construction materials including pre-cast concrete items and stone
Removing some equipment from site
Pumping groundwater from construction site to field
w/c 5 November 2012

Constructing the shaft
Taking deliveries of construction materials including pre-cast concrete items
Removing some equipment from site
Pumping groundwater from construction site to field
Tuesday 6 November 2012 - we will be taking delivery of a wide load. Affected residents will receive a letter asking them not to park on the proposed route of Grenville Road, Lanwithan Road and Coffee Lake Meadow from the afternoon of Monday 5 November

w/c 29 October 2012

Constructing the shaft
Taking deliveries of construction materials including pre-cast concrete items and stone
Removing some equipment from site
Pumping groundwater from construction site to field

w/c 22 October 2012 Construction of the shaft
Taking deliveries of construction materials including pre-cast concrete items
Removing some equipment from site
Pumping groundwater from construction site to field
Concrete pour scheduled for some time this week, details to follow
Friday 19 October 2012 TBC

A large amount of concrete will be delivered to the construction site. This will mean an increase in vehicle movements throughout the day. Deliveries will start at 6.45am and work will take up to 12 hours. 
The delivery route will be along Grenville Road and Two Trees Road to Coffee Lake Meadow and exiting along Lanwithen Road back to Grenville Road.
We will be working hard to minimise any inconvenience this may cause and to complete this phase of the works as quickly as possible.

w/c 15 October 2012Construction of the shaft continuing
Taking deliveries of construction materials including pre-cast concrete sections
Pumping groundwater from construction site to field
Concrete pour scheduled for Monday 15 or Tuesday 16, weather permitting
w/c 8 October 2012

Construction of the shaft continuing
Taking deliveries of construction materials
Removing some shaft equipment from site
Pumping groundwater from construction site to field
Concrete installation to the shaft scheduled w/c 15 October

w/c 1 October 2012

Further stripping of top soil from field next to Coffee Lake Meadow
Construction of the shaft ongoing
Transporting excavated material from shaft to field next to Coffee Lake Meadow
Taking deliveries of construction materials
Removing some equipment from site
Continue pumping groundwater from construction site to field
Delivery of drilling machine and for construction under the River Fowey to Coulson Park

w/c 24 September 2012Stripping top soil from field next to Coffee Lake Meadow
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of construction materials
Removing some equipment from site
Pumping groundwater from construction site to field
Wednesday 19 September A large amount of concrete will be delivered to the construction site. This will mean an increase in vehicle movements throughout the day. Deliveries will start at 6.45am and work will take up to 12 hours.
The delivery route will be along Grenville Road and Two Trees Road to Coffee Lake Meadow and exiting along Lanwithen Road back to Grenville Road.
We will be working hard to minimise any inconvenience this may cause and to complete this phase of the works as quickly as possible.
w/c 17 September 2012

Stripping top soil from field next to Coffee  Lake Meadow
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of construction materials
Removing some equipment from site
Pumping groundwater from construction site to field

w/c 10 September 2012Stripping top soil from field next to Coffee  Lake Meadow
Excavating final soil from shaft
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of construction materials, including reinforcement and cement
Removing some equipment from site
w/c 3 September 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating final soil from shaft
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of construction materials, including reinforcement and cement
Removing some equipment from site
Pumping groundwater from construction site to field

w/c 27 August 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating shaft
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of construction materials
Pumping groundwater from construction site to field

w/c 20 August 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating shaft
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of shaft rings and general construction materials
Pumping groundwater from construction site to field

w/c 13 August 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating shaft
Constructing shaft
Transporting excavated material from shaft to field next to Coffee  Lake Meadow
Taking deliveries of shaft rings and general construction materials
Pumping groundwater from construction site to field

w/c 6 August 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating shaft
Preparing to construct shaft
Transporting excavated material from shaft to field next to Coffee Lake Meadow
Taking deliveries of shaft rings and general construction materials
Pumping groundwater from construction site to field
Taking deliveries of concrete ready for pouring on Tuesday 7 August

w/c 30 July 2012

Stripping top soil from field next to Coffee  Lake Meadow
Excavating shaft
Preparing to construct shaft
Transporting excavated material from shaft to field next to Coffee Lake Meadow
Taking deliveries of shaft rings and general construction materials
Pumping groundwater from construction site to field
Taking deliveries of concrete ready for pouring on Thursday 2 August and Monday 6 August

w/c 23 July 2012

Installing crane next to shaft
Stripping top soil around the shaft
Stripping top soil from the field, ready to receive excavated material from shaft
Starting to excavate the shaft
Preparation works for shaft construction
Transporting excavated material from shaft to field
Starting to reprofile the field with excavated material
Taking deliveries of shaft rings and general construction materials
Continuing to move excess ground water from site to field

w/c 16 July 2012

Crane and excavator arrive on site (planned for 18/7/12) via route shown on website
Installing crane foundation next to shaft
Finishing installing de-watering equipment
Commencing de-watering
Stripping top soil around the shaft
Stripping top soil from the field, ready to receive excavated material from shaft
Starting excavating the shaft
Preparation works for shaft construction
Transporting excavated material from shaft to field
Starting to reprofile the field with excavated material
Taking deliveries of shaft rings and general construction materials

w/c 9 July 2012Continuing construction of access road and temporary compound (near completion)
Constructing storage area within the field near shaft
Stock fencing works in field adjacent to site access
Setting up temporary site office
Erecting site signage at main gates
Taking deliveries of de-watering equipment and setting up equipment
Taking general site deliveries to complete site set up
Taking deliveries of materials for shaft construction work
w/c 2 July 2012

Continuing construction of access road and temporary compound
Continuing to strip top soil
Constructing storage area
Setting up temporary site office
Widening junction of Two Trees Road and Lanwithan Road
Trimming tree branches along Lanwithan Road
Erecting site signage at main gates
Taking delivery of de-watering equipment
Starting to de-water site next to shaft
Erecting timber fence

w/c 25 June 2012

Continuing to record condition of properties in Coffee Lake Meadow
Continuing construction of access road and temporary compound
Continuing to strip top soil along access route
Ongoing construction of access road
Setting up temporary site office
Continuing to establish passing and holding bay on Two Trees Road
Erecting site signage at main gates

w/c 18 June 2012

Continuing to record condition of properties in Coffee Lake Meadow
Continuing construction of access road and temporary compound
Continuing to strip top soil along access route
Ongoing construction of access road
Setting up temporary site office
Erecting site signage at main gates
Establishing passing and holding bay on Two Trees Road

w/c 11 June 2012Erecting information board
Fully recording condition of properties in Coffee Lake Meadow  
Starting construction of access road and temporary compound
Continuing to strip top soil along access route
Ongoing construction of access road
Setting up temporary site office
Meeting with residents liaison group
w/c 6 June 2012

Initial recording of condition of properties in Coffee Lake Meadow
Erecting signs for construction traffic access route to site
Delivering small plant and equipment to site
Breaking through hedge  to Coffee Lake Meadow
Stripping top soil along access route  
Erecting temporary fencing around site access and compound areas 




foot flourish image
  Accessibility | Copyright | Help | Privacy and Cookies | Site map | Terms and Conditions | Mobile Mode | A Pennon Group Company 
© South West Water Limited Registered office: Peninsula House Rydon Lane Exeter Devon, England EX2 7HR Registered in England No. 02366665.