Self Lay

Banner image

As an alternative to having new mains and service connections installed by us, developers can arrange for the work to be carried out by qualified contractors.

A National Code of Practice is now available. This Code of Practice is for when a Developer appoints an independent Self-Lay Provider (known as SLP) to undertake the contestable work of designing and/or installing water mains and services on a new development site. It details processes, requirements for the work and specifies the role of SLP's and Water Companies. Additionally you can find guidance from Ofwat on Self Lay here.

The work must be carried out by a company that is accredited with the Water Industry Registration Scheme (WIRS) which is administered by Lloyds Register.

Developers may wish to request that we carry out a Pre Development Capacity Enquiry for proposed developments to ensure there is adequate capacity within the clean water network.

As an alternative to having new mains and service connections installed by a Self Lay Organisation, developers can arrange for the work to be carried out by us. 

Flowchart and charges

Information on our Self Lay Charges can be found here.

Please view our Flowchart - Self Lay of water mains and services

Design practices and guidance

To assist with the installation of water mains and services, Water UK and the Homebuilders Federation (HBF) have agreed best practice principles for the design of on-site water mains constructed specifically for the purpose of new water connections to new build premises.

Please click here for more information and search for 'Water mains - best practice design principles'.

Standard details:

Standard detail - Sluice Valve 

Standard detail - Through Bore Hydrant

Should you wish to discuss these requirements, please contact the team.

Self Lay application and guidance notes

You can apply for a self lay provision using our Self Lay Application Form. Please see our guidance notes to assist with completing this form.

Please complete all sections and provide the information requested so that your application can be processed as quickly and accurately as possible.

Schedule or permissible materials and construction arrangements

Contestable/Non-Contestable Activities

Below is an extract from the Self lay Code of Practice Version 3.1 – dated May 2017 to cover the non-contestable activity.

The Water Company should allow the SLP to do all elements of work to provide water supplies to New Developments other than those defined as non-contestable in Table 1.

Table 1: Non-contestable activities in the design and construction of water mains and services

DESIGN
Design work for network reinforcement
Sizing pipes - Water Companies retain responsibility for this part of the design work (See Sections 3.5.3 and 3.6.3)
DESIGN APPROVAL
Approving on-site water distribution designs (except where self-certification arrangements are in place)
INSTALLATION
Network reinforcement works (i.e. to secure an adequate supply to the site) whose construction heightens the risk of damage to existing water distribution systems or interrupting supplies to existing customers.  (See note below)
Mains connections that involve heightened risk to existing assets or could affect supplies to existing customers.  (See note below)
Source of water connection to Water Companies' existing assets
Service connections larger than 63mm diameter.
Service connections less than 63mm on existing mains where the Water Company assess that the condition of the main or the material heightens the risk to existing assets or could affect supplies to existing customers. (See note below)
COMMISSIONING
Decommissioning redundant mains following a diversion.


Note - Restrictions on SLPs undertaking work apply when the Water Company assesses that the construction works significantly heightens either the risk of damage being caused to their assets.

Should you wish to discuss these requirements, please contact the team.

 

 

How to notify us

Our performance

There is a set of standards produced by Water UK that measure our performance for our Developer Services activities and the results are published on a quarterly basis. 

Please click here for more information.

Contacting the team

All enquiries regarding Self Lay should in the first instance be addressed to:

Lee Green
Assistant Project Manager
South West Water
Peninsula House
Rydon Lane
Exeter EX2 7HR

Or email us.

Should you wish to arrange a free call back or make a complaint please click here.

How can we help

Quickly find what you are looking for...

Developer services View all
View all