Latest update
7th September 2026
Works are progressing well in Chardstock, with teams continuing installation of the new water main around Hawkchurch, All Saints and Smallridge. Road closures remain necessary in some locations while these essential improvements are completed. Access for residents is being maintained where possible.
17 April 2026
Work is currently underway in Chardstock, both within fields and along local roads, to install new water mains. This is part of our ongoing programme to improve the reliability of your water supply.
Our investment
We are investing in essential upgrades to the water network serving Chardstock and the surrounding area. This project is part of the wider East Devon Mains Replacement Programme, which will replace around 50km of older mains across seven District Metered Areas.
In Chardstock, we are replacing aging water mains. These older pipes are prone to leaks and bursts, which can lead to supply interruptions and emergency repairs. By replacing them with modern, durable materials, we are helping to secure a reliable water supply for homes and businesses in the area for many years to come.
Traffic management
|
Date |
Activity |
|---|---|
| Until Sunday 20 September 2026 | Springhayes to Jubilee House, Chardstock - Road Closure |
| Until Friday 18 September 2026 | Wych Court / Sewage Works to Wytch Green, Hawkchurch - Road Closure |
| Until Friday 18 September 2026 | Brimley Road section, Hawkchurch - Road Closure |
| Monday 31 August to Sunday 20 August 2026 | All Saints Church to All Saints Cross - Road Closure |
| Monday 31 August to Sunday 20 August 2026 | Badgers Rest to All Saints - Road Closure |
| Monday 31 August to Sunday 20 August 2026 | Byways, Smallridge - Road Closure |
Traffic management and access
Some temporary disruption may be unavoidable. Short-term road closures, traffic management or diversion routes may be required for safety.
Access to homes and businesses will be maintained wherever possible. Any work affecting access will be communicated to residents and landowners in advance. Public rights of way and bridleways will remain open with safe access provided.
We will work closely with Devon County Council Highways to minimise inconvenience wherever possible.
What the work involves
The work will take place across public highways and private land throughout the Chardstock DMA.
Where possible, we will use modern trenchless techniques, including directional drilling and pipe bursting, to minimise digging and reduce disruption. In some locations, traditional open-cut methods will be needed. Excavations will be kept to a minimum, and all roads, footpaths, and verges will be reinstated efficiently.
Environmental protection
Protecting the local environment is a key part of the project. Trenchless techniques reduce ground disturbance, helping protect hedgerows, mature trees and farmland.
Environmental and ecological specialists will monitor sensitive areas as required. Works near watercourses, including river crossings, will be carefully managed with the necessary permissions in place.
Project timeline
The scheme is planned to start on 16 February 2026 and is expected to take around six months.
Customers in affected areas will receive updates before work starts, and progress updates will be posted on this page throughout the project.
The project is being carried out by our partners, Clancy. If you have any questions, you contact the Customer Liaison Officer, Jessica Veacock on 07851 256622 or our Customer Services Helpline on 0344 346 2020 between 8am and 6pm, Monday to Friday. Please only call outside of these times if there is an emergency.